Corrugator Machine Preheater (MPH) and Gluer Installation

A customer had purchased a new 3 roll preheater and gluer from Italy for their corrugated cardboard manufacturing facility in Auckland. Concentric Engineered Solutions was involved with the project from the beginning and undertook the following services:

  • Machine layouts for integration with the existing line using a combination of supplied 3D models and site measurements.
  • Design and manufacture of walkways, machine frames & components to integrate the new equipment with the existing.
  • Installation of the manufactured equipment.
  • Positioning and levelling of the new equipment.
  • Project management of the above work.

The equipment arrived in time for the Coronavirus Pandemic and being an essential service (food packaging), the installation was completed under lockdown restrictions.

This job was undertaken with Matched Ltd